Price the hike before it eats the job.

Pick the Producer Price Index series for your material, the bid month and the purchase month. See whether your clause triggers, what it pays, and copy draft clause language for your attorney.

Updated Nov 25, 2026Not tax or legal advice

Index
Clause terms
Live result
Escalation adjustment+$22,336
Clause triggered

Steel mill products moved +32.9% from Oct 2025 to Oct 2026. Applied: +27.92% of $80,000.

Index change+32.9%300.7 → 399.6
Applied+27.92%excess over trigger
Revised material cost$102,336was $80,000
Steel mill products (BLS PPI WPU1017)Jul 2025Oct 2026±5% band
BLS PPI WPU1017, not seasonally adjusted. Shaded: the no-adjustment band. The latest four months are preliminary and can be revised.
Draft for review
Material Price AdjustmentGenerated by Sub Desk

1. Covered materials. The Contract Price includes $80,000 for structural steel and rebar (the “Covered Materials”), priced from supplier quotes current at the time of the bid.

2. Index. Price changes are measured with the U.S. Bureau of Labor Statistics Producer Price Index series WPU1017 (Steel mill products), not seasonally adjusted (the “Index”). The base Index is 300.665 for Oct 2025.

3. Adjustment. If the Index for the month the Covered Materials are purchased differs from the base Index by more than 5%, the Contract Price will be adjusted by the percentage change in the Index in excess of 5%, multiplied by the cost of the Covered Materials. Decreases beyond the same threshold will be credited to the Owner on the same basis.

4. Support. Contractor will submit the published Index values and supplier invoices with any request. Adjustments are made by change order, apply only to the Covered Materials, and do not add markup unless the parties agree in writing.

5. Index changes. If the Index is discontinued or rebased, the parties will use the successor or closest comparable published series.

Sample language to discuss with your attorney. Not legal advice; check your contract, your state, and any public-work rules.

Get the next one in your inbox

Short bid-math notes for subs: rate changes, index moves, one tool at a time.

You’re joining the free Desk briefing on Substack (published by Small Deal Desk): Sub Desk bid-math notes and the Pro waitlist. Confirm the email Substack sends. Unsubscribe anytime.

Result…See it

How it is calculated

Nothing here is a black box. These are the exact formulas the calculator runs on our server.

Index changecurrent index ÷ base index − 1. Base = the bid month; current = the month the materials are bought.
Trigger bandNo adjustment while the change stays within ± the trigger. Shared risk inside the band is what makes owners accept the clause.
Pay the excess (default)applied = change − trigger (change + trigger for decreases)
Pay the full changeapplied = the whole change once the trigger is crossed
Capapplied is limited to ± the cap, if you set one
Adjustmentmaterial cost × share covered × applied. One-way clauses ignore decreases; two-way clauses credit them.

Worked example

Labeled example

Steel on an $80,000 package. Bid on BLS PPI WPU1017 (steel mill products) in October 2025, bought in October 2026. 5% trigger, pay the excess, no cap.

Index300.665 → 399.645
Change+32.9%
Applied (beyond 5%)+27.92%
Adjustment owed$22,336
With no clause, the sub absorbs$26,336

Limits

The calculator uses your inputs and the published figures named on this page. It does not know your exemption certificates, owner type, class codes, carrier, contract language or local rulings. Use it to price and to ask better questions; confirm the answer with your state, your CPA, your agent or your attorney.

Questions

What is a material price escalation clause?

A contract term that adjusts the price of specific materials if a named, published price index moves more than an agreed amount between the bid and the purchase. It moves volatile-commodity risk out of the bid contingency and into a measurable formula.

Which index should I use?

The most specific BLS Producer Price Index series that tracks what you buy: steel mill products for rebar and sheet, softwood lumber for framing, nonferrous wire and cable for building wire, ready-mix concrete, gypsum products and so on. Name the series ID in the contract.

What is a reasonable trigger?

Many clauses use 3–10%. A band shares small swings between the parties and saves the clause for real moves. A cap limits the owner’s exposure and makes the clause easier to accept.

Are recent PPI numbers final?

No. BLS marks the latest four months as preliminary and can revise them. Clauses often say which release controls.

Is the generated clause legal advice?

No. It is sample language to start a conversation with your attorney. Enforceability depends on your contract, your state and, on public work, the agency’s rules.